Project based manufacture doesn’t get much
bigger than shipbuilding. Sea Master Consulting
& Engineering SL installed Sescoi’s MyWorkPLAN
job management software to help it control the
cost and delivery lead times of its naval
engineering and design contracts. Located in El
Puerto de Santa Maria in Southern Spain, the
company was formed in 2007 by a group of
engineering professionals with extensive
experience in the shipbuilding sector, to provide
pre-contract designs, technical proposals,
evaluations, risk analyses and assistance with
stability, dock and sea trials as well as providing
expertise in solar power generation plant designs.
<< Keeping track of cost,
planning and workload
was both a chore and
unreliable. These tasks
have now been automated
producing accurate figures
and saving hours of work >> Luis Labella, Director at Seamaster
Luis Labella, Director at Sea Master says, “We
have a large number of varied projects
running simultaneously so, before we
installed MyWorkPLAN, it was difficult to keep
track of progress and identify the resources
required by each of them. Our aim is to
establish ourselves as a market leader in the
shipbuilding and solar power generation
sectors, so we needed the right management
systems to improve efficiency.”
Sea Master evaluated MyWorkPLAN, on-line
and through a series of web based
demonstrations, so face-to-face meetings were
not necessary. Engineers from the company
then installed and implemented the software
themselves, purchasing it following a successful
subscription period. Luis explains, “It was a
supremely easy implementation. The
software is very intuitive with standard
reports which cover nearly all our needs. The
learning curve for users is virtually zero.”
Naturally, Sescoi has project managers dedicated
to managing MyWorkPLAN implementation.
However, the ease with which Sea Master’s
engineers installed the software themselves
shows how simple it can be to integrate and
implement.
Sea Master prides itself in the high
levels of expertise which it can offer
to its customers, so the manual
methods it was using to control
its projects were a serious drain
on valuable human resources.
Luis says, “Keeping track of cost, planning and
workload was both a chore and unreliable.
These tasks have now been automated
producing accurate figures and saving hours
of work. We are also achieving major
improvements in the reporting of our key
performance indicators, resulting in
significant cost savings and more efficient
project management.”
MyWorkPLAN integrates with many existing
office based software systems, such as
Microsoft Excel®, as well as with popular
accounting packages, enabling it to utilize
existing knowledge and data which has been
built up by users, and then share it around the
organisation. Its ability to automatically collect
real-time information greatly reduces
administrative effort and increases the accuracy
of the data collected. CAD models imported into
the system can be analyzed and viewed in a
tree structure arrangement so that, when
combined with historic information, engineers
can prepare highly accurate quotations.
Furthermore, the planning module enables a
company to monitor the workload on each of its
resources, helping it to predict realistic delivery
times. Luis adds, “In addition to providing
technical excellence, we need to meet
deadlines and provide our customers with
exceptional service in order to achieve our
aim of becoming a market leader. With
MyWorkPLAN we have a precise assessment
of our workload, enabling us to provide very
accurate tenders. It has produced a huge
improvement in our customer service levels.”
|